Key Issue System

85%

Status

On Hold [On Hold]

85% complete, updated on Fri 9/9/16 4:33 PM by Greg Porter

The customer is continuing to audit key data. It is anticipated that they will be ready to start entering some data in the December/January 2016 time frame.

Details

Dates
Tue 10/14/14 - Fri 5/29/15
Acct/Dept
ABA - Administration and Business Affairs
Type
Project / New Development
Health
On Hold
On Hold Until
Fri 10/30/15
Requirements
Implement the Simple-K Key Management Software that has been purchased by Facilities Services
Created
Wed 10/1/14 11:04 AM
Modified
Fri 8/3/18 3:00 PM
Problem / Opportunity
Briefly summarize the problem or opportunity you propose to address. Write this in terms of the organizational problem being addressed, not in terms of the solution needed.
Implement the Simple-K Key Management Software that has been purchased by Facilities Services
Key Issue is currently handled through SiteMaster, an old software program that possesses none of the conveniences, securities or flexibilities of today’s software.
Goals & Objectives
Objectives are specific, measurable, and timed outcomes of the project that are stated in terms of the problem solutions or opportunities users will experience.
All hard keys are managed via the Simple K Software.
Risks and Dependencies
Identify any factors that can affect the outcome of the project including major dependencies on other events or actions. These factors can affect deliverables, success, and completion of the project.
Work and other resources required may be more than IRT can afford to provide
The old system may fail before a new solution is implemented

Description

Implement the Simple-K Key Management Software that has been purchased by Facilities Services
Key Issue is currently handled through SiteMaster, an old software program that possesses none of the conveniences, securities or flexibilities of today’s software.

Systems Affected

  1. Common Managment System(CMS)- HR

    A feed from CMS-HR will be required

Manager