Capital Public Radio Infrastructure Upgrade

50%

Status

On Hold [On Hold]

50% complete, updated on Mon 10/2/23 7:16 AM by Nick Sladojevic

Changed Status from In Process to On Hold.
Changed Health from Red - At risk with no corrective actions to On Hold.

Details

Dates
Fri 7/1/22 - Wed 5/31/23
Acct/Dept
IRT - Project Management Office
Service
Project Request / New Project Request
Type
Project / Annual Project Call
Health
On Hold
Portfolio(s)
Created
Fri 6/10/22 1:01 PM
Modified
Mon 10/2/23 7:16 AM
Link to Strategic Planning and Mandates
This will link the project to the University strategy it supports. If it is not a strategic project, don't select any.
Community Collaboration Imperative
Problem / Opportunity
Briefly summarize the problem or opportunity you propose to address. Write this in terms of the organizational problem being addressed, not in terms of the solution needed.
Capitol Public Radio is moving and IRT needs to provide them with the infrastructure set up. Also, Sacramento State IRT will start supporting Chico radio station.
Goals & Objectives
Objectives are specific, measurable, and timed outcomes of the project that are stated in terms of the problem solutions or opportunities users will experience.
1. Two Memorandums of Understanding (with Chico and CPR)
2. Network connectivity in the downtown bldgs
3 Network connectivity to Chico
4. Network design.
5. Internal network equipment and support ( wiring, labeling the jacks, phones, internet, TVs, etc.)
6. Domain migration
7. Server support
8. Service Desk support
9. Desktop imaging.
Area Lead
The person in your area who will help lead the following: document requirements, bring in appropriate resources (e.g., faculty, students, staff, etc.), and oversee tasks, testing, and training.
Ted Koubiar
Functional Teams and Other Resources
Please do your best to define personnel needed for your project, as well as your best estimate of the number of hours needed from those project team members.
IRT: Brandon Oreno, Rich Power, Kevin Reddell, Carl Oakes, James Estes, Ben Vanovereem, Ted Koubiar
Executive Sponsor
Each project must have an executive sponsor (VP / Cabinet level executive).
Mark Hendricks

Description

To upgrade infrastructure for the new location of CPR.

Manager

Sponsor