In Process [In Process]
35% complete, updated on Wed 5/1/24 9:44 AM by Ange Bledsoe
Changed Percent Complete from 30% to 35%. Recent Activities: PO submitted on March 29, 2024 Test server builds are 100% complete System architecture diagram is 95% complete Shared system diagram with vendor to review & validate Key Upcoming Tasks: Receive estimated delivery date for hardware Build production environment (test is complete) Receive validation of system architecture from vendor Finalize and create firewall rules Provision vendor accounts for server configuration Vendor to configure servers and install necessary software Test hardware (Housing has a lock and reader on site) Cutover/go live on new system Decommission old servers Create the install schedule with Siemens Receive assigned PM from Siemens Risks/issues: An estimated hardware delivery date has not been provided Overlapping projects (wifi upgrade and fire system upgrade) Lack of/very slow response from CAR