In Process [In Process]
30% complete, updated on Wed 5/1/24 10:42 AM by Vikram Chidambarasundaram
Completed Tasks: Completed cloning the current OnBase PROD database to TEST (March 1st) Held project kickoff meeting with Konica Minolta (April 8th) Conducted discovery phase activities (April 8th-15th) Established test system environment and completed upgrade (April 16th-30th) Key Activities Planned: May 1st-15th: Finalize system readiness and conduct User Acceptance Testing (UAT) May 1st-20th: Create the production system environment. June 3rd-8th: Migrate and upgrade production system. June 9th-30th: Go-live and provide post-implementation support. Project Management Tool: Active Collab will be utilized for document storage and issue tracking throughout the project lifecycle.
Upgrade OnBase to EP6. Fixes bugs, and enables the team to take advantage of new features/functionality. With EP6 we will be able to purchase and leverage the Adobe Sign integration. Project start in July/August 2022 Time frame cut over in January 2023.